C-level bc.game review of Unit 11 of Cathay Power Generation Company is in order
Source: Hebei Construction Investment bc.game review Time: 2023-05-22

Recently,Cathay Power Generation Company Unit 11 C-level bc.game review enters the 13th day,All bc.game review tasks are carried out in an orderly manner。

Steam turbine major,Host #5、#6 bearing bush and sealing bush have been inspected and measured,Having conditions for wind pressure;Condenser、Oil cooler、The flushing of heat exchange equipment such as closed coolers has ended;#11 machine side auxiliary steam header contact door bc.game review work has been completed;Gaojia vent pipe modification、The work of replacing the seal of the condensate pump is in progress,Metal monitoring project in progress。

Electrical Major,Boost station related switches、Knife gate bc.game review、The battery replacement of Unit 11 Group I has been completed;Upgrading and transformation of generator and transformer unit、Generator excitation system bc.game review、High voltage motor and frequency converter bc.game review、Inspection and bc.game review of factory electrical bus switches and distribution devices、The bc.game review and testing of the electrical equipment of the detachment system is steadily progressing,The next step will focus on equipment reassembly and protection device transmission。

Boiler Professional,A total of 44 rows of secondary superheater outlet pipes in the heating surface modification,Reinstalled row 22;The third layer of the horizontal reheater has completed the removal, wear and explosion-proof inspection,332 pipes exceeding the standard need to be replaced,282 have been replaced;26 sampling tubes have been sent for inspection;All the old heat storage elements of the preheater have been lifted out,New components are being reinstalled;The old ammonia spray grille has been removed in the liquid ammonia to urea project,The new grille reinstallation work is in progress;Catalyst module replacement work is 80% complete。

Thermal Control Professional,Completed the verification of more than 130 key instruments and economic instruments,Complete control system bc.game review and switching test、Fume system bc.game review、Low voltage ride through device bc.game review、15 standard bc.game review items including boiler fuel ignition system bc.game review。

Safety measures for inspection personnel at the bc.game review site are in place,The person in charge of each stall will monitor carefully,Relevant management personnel keep an eye on the scene,Watch the progress、Check quality,Tense and orderly;All bc.game review departments strictly implement various measures,Carefully investigate safety issues that arise on site,Communicate with relevant departments in a timely manner、Coordinated solution,Ensure that all bc.game review work is carried out safely and smoothly。

(Xingtai Power Generation CompanyContributed by Li Huijuan)